The new parking system was first proposed to businesses in the city in 2005. Since
then there have been some changes to the idea - the zone boundaries have been moved slightly, so that
they match those of the Emergency Planning Map.
The zone symbols have also
been altered so that they meet the Department for Transport’s guidelines.
We
have taken a huge leap forward with the project by getting all city centre car park operators on board
with the proposals. A pilot scheme is in progress on the A611, featuring digital display boards and
multi purpose digital cameras; the digital display boards provide up to the minute traffic information
and the digital cameras monitor traffic flow.
For example, we can now
accurately tell motorists on the A611 up-to-the minute journey times for the route into the city centre
and inform them of any road incidents or delays.
|
Below is
a list of the various stages of ParkSmart
|
|
Car Park Operators
agree to the proposals in principle - Completed
|
|
Boundaries and sign symbols agreed
and finalised - Completed
|
|
Department for Transport approving the proposals - Completed
|
|
Nottingham
City Council approval - Completed
|
|
Park & Ride facilities - Completed
|
|
Pedestrian
signing implementation - Due to start April 2008
|
|
Car park occupancy signing implementation
- Due to start April 2008
|
|
Information boards introduced - Ongoing
|
|
Local
business involvement - Ongoing
|
The
completion
of ParkSmart, including the new signs and technology, is scheduled for March 2009.